Carryover Work Can Undercut Next Year’s Plan

Carryover Work Can Undercut Next Year’s Plan

The remediation program appeared in the planning baseline, with funding, staff and an expected completion date. Its lead said the date remained achievable unless a final regulatory review brought additional work. Leaders accepted that assumption and ranked the new proposals against what they believed was the remaining capacity.

In the first weeks of execution, further regulatory findings kept several risk, legal and data specialists tied up. One approved priority needed those same people. Its funding and start date remained in place, but specialist reviews slipped, meetings multiplied and decisions slowed. Project leads moved milestones, finance held back some spending, and senior leaders had to resolve clashes between commitments they thought planning had settled.

The issue was not simply that carryover work had been overlooked. It was visible, but its claim on capacity was treated as fixed. Leaders had made new proposals compete with one another without asking whether the older program should retain the same people and budget rather than give way to a new priority.

A carryover line in the plan can improve visibility without changing that dynamic. Unless old and new work are assessed together, the plan is an inventory, not a complete capacity decision. The tradeoff then arrives during execution, when both commitments are approved and specialists are already needed on both sides. In this case, the plan’s problem was not a poor ranking of new initiatives; the choice over competing commitments had been postponed.

Share

Comments (0)

Leave a comment

No comments yet. Be the first!